Case study: London's Olympic network from BT

After receiving an honourable mention in the European user awards for networking, Computer Weekly looks at the challenge of rolling out the network for the London Olympic Games in 2012

This article can also be found in the Premium Editorial Download: CW Europe: Data speeds Mercedes F1 around the world

In the summer of 2012, all eyes were focused on London as the world’s greatest sporting event took over the capital city. With almost 27 million viewers of the Olympic Games opening ceremony in the UK alone, the pressure was on to get the whole event right, from building the venues in time, ensuring public transport could cope and winning medals, through to the underpinning technology.

After a long and hard-fought tender process, BT was awarded the contract at the end of 2007 to provide networking for all the sites, in London and across the UK, and to ensure everyone from press to athletes and, of course, the spectators, would be able to stay connected.

But it was not only the visitors to the Olympic sites who depended on the network. It was needed by millions of spectators around the world so they could watch and share in the experience wherever they were.  

With this mammoth task, four years for planning does not seem like a long time.

Tim Boden, the technical director of the Games – who is now back in his day job of solutions director for the Unilever account at BT – tells Computer Weekly about the long process to secure and deliver the contract.

“I joined BT in 2006, just after the invite to tender had been published. A long-list was released in March 2007, but it took a long time to be narrowed down to two, which I believe was us and France Telecom – or Orange Business Services as it is represented here,” he says.

“It took a further nine months of negotiations before we were selected in December 2007, meaning the whole process took about 18 months.”

Four or five years out, it looks like a normal telecoms contract, albeit for a high-profile case and with certain service levels that had to be guaranteed

Tim Boden, BT

Staffing a huge networking project

When the deal was done, BT became responsible for all the Olympics networking needs, from wide area networks (WANs) to local area networks (LANs), wireless LANs to mobile services, and everything in between.

This needed a strong team that, although grew in size throughout the process, began at a very modest number for such a mammoth task.

Planning began in the wake of the Beijing Olympics, with a team of between 25 and 30 staff, says Boden. Two years later, when it had finished the designs, the tech team grew to between 50 and 60 staff.

“When the first project needed to go live – in fact it was LOCOG’s (London Organising Committee of the Olympic and Paralympic Games) offices – in April 2010, we had 100 people, and when the Games were a year out we had grown again to 250,” he says.

However, it was in the final weeks and months that the staff numbers exploded and the challenge of managing people became one of Boden’s biggest issues.

“When we were starting to roll out for the test events, things really began ramping up and we had around 850 people for the duration,” says Boden.

“Four or five years out, it looks like a normal telecoms contract, albeit for a high-profile case with certain service levels that had to be guaranteed. However, the whole process of managing those people and training them up took the best part of two years' planning to find a way of getting those additional 550 people completely functional in a three-month window,” he says.

BT decided to use only existing BT employees, rather than hiring in contractors, offering the roles as rewards for good performance in their normal jobs. However, this added another level of strain to Boden and his team, who had to negotiate that time off with existing line managers, get the staff ready and then faze them out when it was time to return to the day job.

Read more about London 2012

Technology-enabled Games

The figures behind the deployment are sizable: more than 5,500km of optical fibre was laid across 94 venues; 11,500 fixed telephones were installed, making and receiving 500,000 calls; and the number of BT Wi-Fi hotspots in London hit 500,000.

All the equipment was provided by Cisco, as one of the lead sponsors of the project, with much returned afterwards. “We put the kit back into somewhere around 60,000 or 70,000 boxes,” says Boden.

But pressures were felt keenly by Boden and his team when time was not on their side.

“In some cases, we could plan around that, as with Horse Guard’s Parade,” he says. “We knew that just six weeks before they were trouping the colour for the Queen’s Jubilee, after which we had to change it into a beach volleyball stadium capable of holding 15,000 and with the networking needed by the press and other dignitaries. That was planned almost to every minute, but definitely hour by hour.”  

Then there were the road-based events, where routes were only closed off very close to the races, so BT had limited time to get everything up and running.

“Venues such as Wimbledon, where just three weeks before the men’s final had taken place, mostly went fine," says Boden. 

The wet spring put it behind schedule on the outdoor venues, however. “For example, in Greenwich Park things were very tight because we couldn’t get power to the venue.”

Beyond the statistics, technology had a profound effect on how people interacted with the Games, and none of that would have been possible without BT

Gerry Pennell, LOCOG

First-class delivery of Olympic coverage

Despite these hurdles, Boden and his team finished on time, and organiser LOCOG was very pleased with the results.

“BT’s major programme approach to right-first-time delivery, risk management and exhaustive testing ensured that all major milestones were delivered on or ahead of time, and as a key technology partner helped enable a first-class delivery of the Games,” says LOCOG CIO Gerry Pennell.

“The global media placed great demands on the IT and telecommunications infrastructure. Feedback from broadcasters was that London 2012 was the best Games service they had experienced – a great testament to the hard work and service levels provided by BT," he adds.

“London staged one of the greatest Olympic and Paralympic Games ever. Beyond the statistics, technology had a profound effect on how people interacted with the Games, and none of that would have been possible without BT, whose commitment to these Games was quite simply spectacular,” says Pennell.

Skills and processes better for BT

But the London Games was always touted as one of legacy. What has Boden and BT left behind that can benefit the UK and its economy?

“All the fibre which supported broadcast at the time has become part of OpenReach – BT’s commercial ISP business – so if you go to Weymouth now, for example, you can get great fibre speeds where there wasn’t any before,” says Boden.

More case studies from Computer Weekly

“The capacity on managed services was upgraded during the Games, meaning we have now been able to upgrade central capacity to support businesses.”

But for Boden, the real legacy of the Games for BT is on the inside of the company.

“Skills and processes will be the big legacy here for BT,” he concludes. “We have developed closer relationships within the business, developed better assurance methods, and improved security from working closely with a number of government agencies. BT will see the benefits.”

Read more on Telecoms networks and broadband communications